Map of construction project districts

Under Construction

I-95 Temple Avenue Improvements, Colonial Heights

Project at a Glance

Begin Date
Feb. 2015

Est Completion Date
Nov. 2017

Phase
Construction

Cost
$20 million

Contractor
Allan Myers, formerly American Infrastructure-Va. Inc.

Locality
Colonial Heights

District
Richmond

Contact
Harold Dyson, P.E., construction manager
(804) 720-7471

Project update & traffic impacts

For the week beginning May 31, crews will use single lane closures during overnight hours between 8:30 p.m.-6 a.m. on Temple Ave. for continued median work. The lane closures will extend between Hamilton Ave. and Conduit Rd. Drivers can expect minimal delays.

Additionally, Ridge Rd. remains closed at Temple Ave. for the duration of the project. Drivers can follow the short posted detour: take N. Temple Ave. back to Ridge Rd.

Weather permitting, traffic will be shifted slightly to the right heading westbound on Temple Ave. early next week. 

At least one travel lane in each direction will remain open on Temple Ave. at all times during construction. Drivers are encouraged to use an alternate route to avoid delays. Project photos are now available.

Subscribe for email updates.

Traffic impacts

Monday, May 30
No scheduled lanes closures.

Tuesday, May 31

Temple Ave./Rt. 144 west (Colonial Heights) – A single, alternating lane will be closed from Conduit Rd. to Hamilton Ave. from 8:30 p.m. Tuesday to 6 a.m. Wednesday for median work.

Ridge Rd. will be closed at Temple Ave. Drivers can follow the posted detour for the duration of the project: Use N. Temple Ave. back to Ridge Rd.

Wednesday, June 1
Temple Ave./Rt. 144 east (Colonial Heights) – The right lane will be closed from Hamilton Ave. to Conduit Rd. from 8:30 p.m. Wednesday to 6 a.m. Thursday for median work.

Temple Ave./Rt. 144 east turn lane to I-95 (Colonial Heights) – The right turn lane from Temple Ave. east to I-95 will be closed from 8:30 p.m. Wednesday to 6 a.m. Thursday for median work. Drivers can access I-95 from the signalized intersection.

Ridge Rd. will be closed at Temple Ave. Drivers can follow the posted detour for the duration of the project: Use N. Temple Ave. back to Ridge Rd.

Thursday, June 2

Temple Ave./Rt. 144 east (Colonial Heights) – The left lane will be closed from Hamilton Ave. to Conduit Rd. from 8:30 p.m. Thursday to 6 a.m. Friday for median work.

Ridge Rd. will be closed at Temple Ave. Drivers can follow the posted detour for the duration of the project: Use N. Temple Ave. back to Ridge Rd.

Friday, June 3

Temple Ave./Rt. 144 east (Colonial Heights) – The left lane will be closed from Hamilton Ave. to Conduit Rd. from 8:30 p.m. Friday to 6 a.m. Saturday for median work.

Ridge Rd. will be closed at Temple Ave. Drivers can follow the posted detour for the duration of the project: Use N. Temple Ave. back to Ridge Rd.Project update

About the Project

This design-build project will realign the entrance and exit ramps at the I-95 interchange at Temple Avenue and replace the signalized intersection with a roundabout. The roundabout will be relocated west of the current intersection and will include two lanes for traffic and a continuous bypass lane on the westbound approach. The I-95 ramps will be extended and improved to provide better sight distance, vehicle capacity and transition from interstate speeds to the Temple Avenue roundabout. This plan will require removing the Temple Avenue bridges to construct the roundabout.

Major project milestone dates:

  • ​Notice to Proceed – February 24, 2015
  • Right-of-way Acquisition Commences – August 2015
  • Final Design Plans – December 2015
  • Utility Relocations – February 2016 to spring 2016
  • Project Construction – March 2016 to November 2017​

Review the project's frequently asked questions.

Review the project's latest design.

Safety improvements

The purpose and need of this project is to improve traffic flow through the I-95/Temple Avenue Interchange, to eliminate prolonged periods of delay and to decrease the accident rate within the project limits. The project will address current deficiencies in capacity, geometry and safety.

Public Involvement

Project partners held a “Pardon Our Dust” public information meeting Wednesday, Feb. 3 at the Colonial Heights Courthouse to discuss construction impacts and traffic management associated with the project.  The meeting brochure and presentation are now available.

 

Why a roundabout?

The roundabout design was chosen as the most efficient design for this congested intersection to provide improved safety and traffic flow. A roundabout reduces traffic and wait times by allowing traffic to continually move at a low rate of speed versus coming to a complete stop at signals. This will be especially important during peak traffic hours. 

The project will realign the southbound and northbound I-95 off ramps to eliminate the existing yield condition. The signalized intersection at the interchange will be removed and replaced with a roundabout.  

The proposed roundabout includes two lanes of circulation and a continuous bypass lane on the west bound approach. Both the northbound and southbound I-95 off-ramps are extended and improved to provide motorists greater distance and improved curvature for transition from the high speed mainline to the arterial. The northbound I-95 off-ramp is improved to provide for a free-flow movement and eliminate the existing yield controlled condition.

How will traffic move through this area?

 

Resources

Public hearing brochure and photos (September 12, 2013)

Photos of the existing interchange on Flickr

VDOT informational brochure

More information about roundabouts in Virginia

Existing roundabouts in the Richmond District

Federal Highway Administration (FHWA) roundabout video

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: May 27, 2016