Map of construction project districts

Proposed

Intersection Improvements at Hopkins and Kingsland Roads in Chesterfield

Intersection improvements to improve safety and capacity

Project at a Glance

Begin Date
Spring 2021

Est Completion Date
Spring 2022

Phase
Design

Cost
$3.4 million

Locality
Chesterfield

District
Richmond

Contact
Jason Zhang, P.E., project manager
(804) 704-3416

Project Description

The primary purpose of this project is to improve safety and traffic operations at the intersection of Hopkins Road (Route 637) and Kingsland Road (Route 611) by constructing a single lane roundabout. The new traffic configuration will reduce congestion and angular crashes at the intersection.

Public Involvement

A public hearing was held on August 29, 2018. A meeting brochure is available.

A citizen information meeting was held on September 7, 2017. A meeting brochure is available.

A citizen information meeting was held on May 24, 2016. A meeting brochure is available.

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Aug. 30, 2018