Recently Completed
Pocahontas Trail over Toe Ink Swamp (Route 60) |
| New Kent County bridge repair |
Project at a Glance
Begin Date
March 2011
Est Completion Date
November 2011
Cost
$589,000
Contractor
Bryant Contracting, Inc - Toano VA
Locality
New Kent
District
Richmond
March 2011
Est Completion Date
November 2011
Cost
$589,000
Contractor
Bryant Contracting, Inc - Toano VA
Locality
New Kent
District
Richmond
Contact
Richmond District
(800) 367-7623
Project details
This project on Pocahontas Trail westbound over Toe Ink Swamp (Route 60) involved the following:
- Replaced the bridge deck to repair structural cracks and spalls and provided an improved reinforced concrete deck,
- Repaired and installed a new traffic safety barrier and railing on both sides of the bridge,
- Replaced the old bridge deck and repaired the cracks and spalls on the sub-structural abutments of the bridge,
- Installed a new traffic safety barrier and railing on both sides of the bridge deck,
- Re-coated/re-painted the existing structural steel girders/beams,
- Replaced the existing pavement – approximately 100 feet on each side of the bridge deck, and
- Installed a new guardrail – approximately 100 feet on both sides of the new pavement.
Project photos on Flickr
How was this bridge rehabilitation project funded?
This $589,000 project was funded with federal and state contributions—80% federal and 20% state. State contributions were allocated from maintenance funds