In Design
Route 360 and Bell Creek Road relocation |
| Projects to improve Route 360 in Mechanicsville |
Project at a Glance
Begin Date
Fall 2014
Cost
Bell Creek Rd. relocation: $8.5 million
Rt. 360 from I-295 to Wynbrook Ln.: $11 million
Lee-Davis Rd. intersection improvements: $13.6 million
Rt. 360 from Lee-Davis to Walnut Grove Rd.: $33.8 million
Locality
Hanover
District
Richmond
Fall 2014
Cost
Bell Creek Rd. relocation: $8.5 million
Rt. 360 from I-295 to Wynbrook Ln.: $11 million
Lee-Davis Rd. intersection improvements: $13.6 million
Rt. 360 from Lee-Davis to Walnut Grove Rd.: $33.8 million
Locality
Hanover
District
Richmond
Contact
Harold Caples, project manager
804-524-6324
What's Being Done
The proposed projects include improvements along Route 360 between the I-295 interchange and Wynbrook Lane, including the relocation of Bell Creek Road.
- Relocation of Bell Creek Road - The current intersection with Route 360 will be moved 650 feet to the east aligning the road with the northern section of Bell Creek Road. The completed road will consist of four through lanes, a raised median, curb and gutter.
- Route 360 between I-295 and Wynbrook Lane - In order to address congestion, VDOT proposes to increase capacity from the current three lanes in each direction to four lanes between I-295 and the proposed Bell Creek Road intersection. Three lanes would remain in each direction between the proposed Bell Creek Road intersection and Wynbrook Lane. However, a continuous through/right turn lane would be added.
Project Updates
Public Hearing Transcript (5 MB) - Feb. 21, 2007
PROJECT SCHEDULE:
- Relocation of Bell Creek Road:
Right of way acquisition and utility relocation = underway
Construction = Fall 2014 - Route 360 between I-295 and Wynbrook Lane:
Right of way acquisition and utility relocation = underway
Construction = Fall 2014 - Lee-Davis Road intersection:
Right of way acquisition and utility relocation = pending funding
Construction = pending funding - Route 360 between Lee-Davis Road and Walnut Grove Road:
Right of way acquisition and utility relocation = pending funding
Construction = pending funding
Page last modified: Feb. 28, 2013