In Design
Route 600/226 Roundabout & Route 1/226 Improvements |
| Project to improve safety and traffic operations in Dinwiddie |
Area Maps
Project Photos
Project at a Glance
Spring 2015
Est Completion Date
Spring 2016
Cost
$7.7 million
Lengths and Limits
0.4 mile
Locality
Dinwiddie
District
Richmond
Contact
Janet Hedrick, project manager
804-524-6146
Project Description
The primary purpose of this project is to improve safety and traffic operations at the Route 1/Route 226 and Route 226/Route 600 intersections.
The signal at the Route 226/Route 600 intersection will be replaced with a single lane roundabout—one 16 foot lane with a five foot sidewalk and a dedicated right turn lane from Route 226 west onto Route 600.
The proposed project includes the widening of Route 226 from approximately 0.10 miles west of Route 600 to Route 1 for a total length of 0.30 miles. The thru lanes will be widened to 14 feet to accommodate bicycles.
Route 1 improvements will consist of minor widening on the west side of the intersection. The length of the 12-foot wide left turn lane onto Route 1 will be extended and the existing right turn lane will be redesigned to improve movements at the Route 1 intersection.
VDOT held a design public hearing for this project on December 1, 2011. public hearing brochure
Project Schedule
Design approval – Winter 2011
Begin right of way acquisition – Summer 2012
Begin construction – Spring 2015
Completion – Spring 2016