Route 114 Widening - Christiansburg

Project at a Glance

Begin Date
Spring 2012

Est Completion Date
Fall 2014

Cost
$24.5 million

Contractor
DLB Inc.

Locality
Montgomery

District
Salem

Contact
Ricky Keith
540-381-7201
Media Contact - Jason Bond
540-387-5493

What's Being Done?

This project will widen one mile of Route 114 (Peppers Ferry Road) at New River Valley Mall in Christiansburg from two to four lanes with turn lanes and improve access management by installing a raised median. 

The project also will include relocating the signal at the mall entrance and building a new Huckleberry Trail bridge over Route 114. 
 

 

Traffic Impacts

On Wednesday, June 25, Somerset Street at Peppers Ferry Road will be closed from 12:30 p.m. to 4:30 p.m. for grading.  Drivers can access Somerset Street using Majestic Drive.

On Thursday, June 26, the entrance to Village Square Shopping Center on Peppers Ferry Road will be closed from 7 a.m. until 8:30 a.m. Drivers can reach Village Square using Somerset Street during the closure.

A new traffic pattern is in place on Peppers Ferry Road from east of Walnut Drive to the BP gas station

Flaggers may control traffic at times for utility operations taking place on Route 114 (Peppers Ferry Road) near the New River Valley Mall. Trucks will be entering and exiting the road in this area. Occasional flagging operations will take place from 10 a.m. until 4 p.m. on weekdays.

For traffic related information visit www.511Virginia.org .

 

 

 