Augusta County – Route 774 Bridge |
Project at a Glance
Begin Date
Project awarded on March 5, 2009
Est Completion Date
November 13, 2009
Cost
Contract value $821,838.00
Lengths and Limits
between Route 608 (Battlefield Road) and Route 775 (Craig Shop Road)
Contractor
Hammond-Mitchell Inc. of Covington, Va.
Locality
Augusta
District
Staunton
Project awarded on March 5, 2009
Est Completion Date
November 13, 2009
Cost
Contract value $821,838.00
Lengths and Limits
between Route 608 (Battlefield Road) and Route 775 (Craig Shop Road)
Contractor
Hammond-Mitchell Inc. of Covington, Va.
Locality
Augusta
District
Staunton
Contact
Project Details
Replace Route 774 bridge. The new structure will be a two-lane, double span, 28-foot wide steel beam and concrete deck bridge with an unrestricted weight limit. This location is on Route 774 (Cline River Road, New Hope), between Route 608 (Battlefield Road) and Route 775 (Craig Shop Road).
Benfits
This will replace a 3-ton weight limit, single-lane steel truss bridge built in 1905. The new structure will have full roadway approaches with shoulders transitioning into the existing stabilized road. The new bridge will have an unrestricted weight limit.
During Construction
Route 774 (Cline River Road, New Hope), between Route 608 (Battlefield Road) and Route 775 (Craig Shop Road), will be closed.
Current Traffic Alerts
Motorists can use the following detour:- Northbound on Route 774, take Route 608 (Battlefield Road) to Route 778 (Knightly Mill Road) to Route 775 (Craig Shop Road) to Route 774.
- Southbound on Route 774, take Route 775 (Craig Shop Road) to Route 778 (Knightly Mill Road) to Route 608 (Battlefield Road) to Route 774.