I-95/I-395 HOV Restriction Study
Meeting Slides - June 30, 1998
Study Objectives
- Optimize use of transportation system through increased person movement in I-95/I-395 corridor
- Alleviate traffic congestion in I-95/I-395 corridor
- Optimize HOV use in I-95/I-395 corridor
Technical Committee
- VDOT
- VDRPT
- Local Jurisdictions / Planning Agencies
- State Police
- Transit Providers
- WMATA
- VRE
- PRTC, NVTC
- Quicks, Lee and National Coach Works
- VPSI
- FHWA and FTA
Consultant Team
Prime Consultant: BMI
Specialty Subconsultants:
- Travesky & Associates, Ltd. - Public Information
- S. G. Associates, Inc. - Transit Issues
- TYLIN International - Engineering
- Gallop Corporation - Demand Modeling
- MCV Associates - Data Collection
- BRW - HOV 0perations
Study Scenarios
Changes to Current HOV Restrictions
- HOV 3+ to HOV 2+ for entire corridor
- HOV 3+ to HOV 2+ for portion of corridor
- Effects of I-395/ I -95/ I -495 construction on switch to HOV 2+
- Allowing PM southbound non-HOV traffic to exit at Franconia-Springfield Parkway
- Extending HOV-restricted time periods
Changes to HOV System
- Effects of adding third HOV lane inside Beltway on HOV 2+ operations
- Transitioning from HOV 2+ to HOV 3+ at Beltway
- Adding HOV ramps at selected locations:
- to/from Rt. 123 northbound
- to/from south at Seminary Road
Operational Measures
- Corridor speeds in HOV lanes
- Travel time/delay in HOV lanes
- Vehicle and person volumes in HOV lanes
- Air quality impacts
Transit Impact
- Ridership
- Revenues
- Operating costs
- Effects of "slugging"
Other Measures
- Safety
- Violation Rates
- Enforcement
Public Involvement
Objectives of the Public Participation Program
- Make public aware of existence, purpose, and scope of project
- Receive input from public on issues and findings of the study
- Report results at key milestones
Selection and Role of Stakeholders
- Individuals and group representatives
- Work, travel, reside within I-95/I-395 corridor
Opportunities for Public Participation
- Telephone Hotline (1-888-395-0095)
- Interactive Web Site on Digital City/America Online