Online Services | Commonwealth Sites | Help | Governor

Welcome
Project Details
Schedule
Weekly Update
Pictures
Contacts

Project Details


This section of road carries an average of 47,000 cars per day.

That number is expected to grow to 54,000 by 2026.

With the intersection of Warwick and J Clyde Morris boulevards already congested during the busiest hours, the road was in desperate need of a makeover.

In order to save money and finish the project as quickly as possible, the Virginia Department of Transportation (VDOT) and officials from Newport News worked together to split construction into three phases.

Phase I – Complete

Oct. 20, 2007 marked the completion of Phase I. Local contractor Basic Construction Co. started work on the $10.2 million project in February 2006 and completed it on time and on budget.

Extensive improvements for the intersection of Warwick and J. Clyde Morris boulevards include:

A new designated right turn lane, from J. Clyde Morris Boulevard onto Warwick Boulevard, added a 600-foot merge lane to help relieve congestion during the evening rush hour and increase safety around Christopher Newport University.

Phase II – Complete

On Dec. 28, 2007, the second phase of the Warwick Boulevard Improvement Project was completed within budget and almost six months ahead of schedule.

Contractor Suburban Grading and Utilities Inc. started work on the $14.5 million Phase II in September 2006 and completed it ahead of the scheduled completion date of June 15, 2008.

This phase incorporated storm water, sewer and water supply line relocation and upgrades on Warwick Boulevard from Nutmeg Quarter to Nettles Drive. 

At the request of the city, an additional $900,000 of work was added to the project to replace completely deteriorated portions of the sewer system.

By working closely with Newport News, VDOT was able to add this scope of work to the existing contract. This saved taxpayers costs and avoided additional construction and negative impacts to the businesses and customers in the corridor.

Phase III - Expected Completion: Winter 2009-2010

Daily changes in final phase will be the most visible to motorists.

Work began in December 2007 and includes: