Schedule

November 2005

CTB awards Phase I to Basic Construction Co. for $10.2 million

February 2006

Phase I begins

July 2006

CTB awards Phase II to Suburban Grading and Utilities Inc.for $14.5 million

September 2006

Phase II begins

October 2007

Phase I complete

November 2007

CTB awards Phase III to E.V. Williams Inc. for $17 million

December 2007

Phase II complete

  Phase III begins

  Winter 2009-10

  Phase III complete