That number is expected to grow to 54,000 by 2026.
With the intersection of Warwick and J Clyde Morris boulevards already
congested during the busiest hours, the road was in desperate need of a
makeover.
In order to save money and finish the project as quickly as
possible, the Virginia Department of Transportation (VDOT) and officials from
Newport News worked together to split construction into three phases.
Oct. 20, 2007 marked the completion of Phase I. Local contractor Basic
Construction Co. started work on the $10.2 million project in February 2006 and
completed it on time and on budget.
Extensive improvements for the
intersection of Warwick and J. Clyde Morris boulevards include:
A new designated right turn lane, from J. Clyde Morris Boulevard onto Warwick Boulevard, added a 600-foot merge lane to help relieve congestion during the evening rush hour and increase safety around Christopher Newport University.
On Dec. 28, 2007, the second phase of the Warwick Boulevard Improvement Project was completed within budget and almost six months ahead of schedule.
Contractor Suburban Grading and Utilities Inc. started work on the $14.5 million Phase II in September 2006 and completed it ahead of the scheduled completion date of June 15, 2008.
This phase incorporated storm water, sewer and water supply line relocation and upgrades on Warwick Boulevard from Nutmeg Quarter to Nettles Drive.
At the request of the city, an additional $900,000 of work was added to the project to replace completely deteriorated portions of the sewer system.
By working closely with Newport News, VDOT was able to add this scope of work to the existing contract. This saved taxpayers costs and avoided additional construction and negative impacts to the businesses and customers in the corridor.
Daily changes in final phase will be the most visible to motorists.
Work began in December 2007 and includes: