Learn More

Route 29-Route 250 Interchange Improvements

What is Proposed?

This project will improve the entrance ramp from Route 29 south onto the Route 250 Bypass by adding an additional lane on the ramp and an associated merge lane on Route 250 westbound to the Barracks Road exit. 

It also adds an additional southbound lane to Route 29 by widening in the median from just south of Hydraulic Road to the Route 250 Bypass interchange.

The improvements are intended to reduce congestion and improve safety and the movement of traffic from Route 29 onto the Route 250 Bypass, as well as the flow of traffic continuing south on Route 29 (Emmet Street) into the city.

Also included in this project is the construction of new sidewalk between Morton Drive and Angus Road. The proposed sidewalk will be located in the U.S. 29 median, which provides the safest route for pedestrians to use when traveling from one side of the interchange to the other. The new sidewalk section will connect with existing pedestrian crossings and sidewalks at Angus Road (north of the interchange) and Morton Drive (south of the interchange).

As part of the environmental review a preliminary noise study was performed and locations for noise barriers were identified along the lanes of the U.S. 250 Bypass between U.S. 29 and Barracks Road.

Following completion of the final noise study affected property owners were polled and the majority favored the installation of noise barriers. A final design for the surface finish of the barriers was selected by the city and Albemarle County in October 2014. Those barriers will be installed along the westbound shoulder between Route 29 and Barracks Road as well as at several locations along the eastbound shoulder.

The project, known locally as the "Best Buy ramp project," is a priority for both Charlottesville and Albemarle County.


Information collected during project scoping supported the proposed improvements to address traffic volumes and crash history. From February 2006 to December 2008 there were 34 crashes on the Route 250 Bypass ramp and its immediate vicinity.

In 2010, Route 29 between Hydraulic Road and the Route 29/250 interchange carried an average of 52,000 vehicles per day. On the Route 250 Bypass from Route 29 west to the Charlottesville city limits, an average of 38,000 vehicles used that road daily.

Development of the project began in 2007 by Charlottesville under the Urban Construction Initiative, with technical engineering work performed by a consultant engineering firm. In June 2011, VDOT assumed management of the project.


June 20, 2012: Citizen information meeting

Nov. 27, 2012: Design public hearing

Dec. 7, 2012: Comment period ended

Fall/Winter 2013: Notice to proceed to obtain right of way and/or easements

Nov. 2014: Advertisement for construction

Jan. 14, 2015: Commonwealth Transportation Board awards construction contract

March 2, 2015: Fielder's Choice Enterprises begins construction

May 21, 2016: Contract fixed completion date


Total Cost: $17,150,000

Engineering of Roadway Plans:

Right of Way Acquisition and Utility Relocation:

$14,303,865 (includes noise barriers)

Cost is subject to change as the design is finalized.





Information and Resources

News releases

Rt. 29 Ramps to Rt. 250 Bypass Closed Overnight Thursday

Construction Begins Monday on Rt. 29 / Rt. 250 Interchange

CTB Awards Rt. 29 / Rt. 250 Interchange Contract

Bids received for Route 29 / Route 250 interchange improvements

Advertisement of Route 29 / Route 250 interchange project kicks off Route 29 Solutions construction 

 Utility Work Begins Next Week on Rt. 29 in Charlottesville

Resources from the stakeholders' meeting, August 2014

Route 29 Current Plans Adobe Acrobat PDF (2 MB)
Route 250 Current Plans Adobe Acrobat PDF (6 MB)
Plan sheets compiled by route and uploaded Aug. 14, 2014

Resources from the Public Hearing, November 27, 2012:

Project brochure

Comment sheet

U.S. 29/U.S. 250 Bypass Interchange Public Hearing Is Nov. 27


Resources from the Citizen Information Meeting, June 20, 2012:

Project brochure

Comment sheet

U.S. 29/U.S. 250 Bypass Interchange Project Public Meeting June 20

Displays (11 by 17 inches):

At a Glance

Begin Date 

March 2, 2015

Contract Completion Date

May 21, 2016


Estimated cost $17.15 million (2015-2020 Six-Year Improvement Program estimate)

Lengths and Limits

0.492 mile; Route 29 intersection at Hydraulic Road south to Route 250 Bypass interchange, 
then west on Route 250 to Barracks Road interchange






Dave Covington