RT. 29 SOLUTIONS LANE CLOSURES
Scheduled activities: Week of July 11-15, 2016
CHARLOTTESVILLE — The following work is scheduled, weather permitting, on the Route 29 corridor in Albemarle County and the city of Charlottesville during the upcoming week. Speed limits may be reduced and traffic movements may be restricted within highway work zones.
(NEW) or (UPDATE) indicate revisions since last week’s report.
Rio Road grade-separated intersection – Major construction on the project is under way. Through September 2, the following traffic patterns will be in effect:
On Route 29 north and south of the Rio Road intersection:
- Between 6 a.m. and 9 p.m., there will be two lanes southbound and three lanes northbound
- Right turns onto Rio Road will be permitted at all times
- No left turns at the intersection at any time
- Between 9 p.m. and 6 a.m., there will be at least one lane open both northbound and southbound
- All business entrances will remain open during business hours
On Rio Road east and west of Route 29:
- Traffic on Rio Road will not be able to cross Route 29
- Right turns onto Route 29 will be permitted at all times
- No left turns at the intersection at any time
- All business entrances will remain open during business hours
Posted detour routes during the construction will be Berkmar Drive to Woodbrook Drive or Hilton Heights Drive, and Hillsdale Drive to Branchlands Boulevard.
Route 29 widening – Construction continues in the median and along the roadway shoulders between Route 643 (Polo Grounds Road) and Route 1719 (Towncenter Drive). Travel lanes are narrowed and shoulders are closed within the work zone and the speed limit is reduced to 40 mph. Intermittent single lane closures Sunday through Friday between 9 p.m. and 6 a.m. Motorists should remain alert and use caution through the work zone.
Berkmar Drive Extended – Construction of bridge abutments north and south of the South Fork Rivanna River and clearing and grading along the roadway alignment continues. Monday through Friday between 7 a.m. and 6 p.m., intermittent lane closures with flagging on Rio Mills Road during construction activities. On Towncenter Drive in the vicinity of the roundabout, motorists should be alert for dump trucks and other equipment entering and exiting the roadway.
(UPDATE) Route 29/250 Bypass interchange – Contractor performing electrical work on Route 250 eastbound. Alternating lane closures will occur between the Barracks Road and Route 29 exits on Monday and Tuesday between 9 p.m. and 6 a.m. Use caution through the work zone.
(NEW) Hillsdale Drive Extended – Installation of construction signs and environmental fencing and controls. Travel lanes may be narrowed and shoulder closures installed intermittently on the following roads: Hillsdale Drive, Hydraulic Road, India Road, Zan Road, Greenbrier Drive, Pepsi Place and Seminole Court between 9 a.m. and 4 p.m. Monday thru Friday. Motorists should remain alert and use caution through the work zone.
More information about these projects, and other Route 29 Solutions projects, can be found on the project website, www.Route29Solutions.org. Information about other Culpeper District activities that will affect traffic is also available on Twitter at @VaDOTCULP and on VDOT’s website at: www.virginiadot.org/travel/travel_alerts/culpeper/default.asp.
(END)