Recently Completed: Routes 11 and 19 in Abingdon (Washington County) Intersection Improvements

SMART SCALE Dashboard

Cost and schedule ►

The Route 11/19 intersection improvement project in Abingdon was completed late fall 2021. The goal of the project is to improve traffic flow by adding a second right turn lane from Route 19 onto southbound Route 11, as well as traffic signal changes to accommodate the second right turn lane. 

Benefits 

The project will improve traffic flow at this busy intersection in Abingdon.

Major Milestones 

Construction began Summer 2021 and wrapped up late fall 2021.

Resources

Contact Info:

Anthony Wilder, Construction Manager
276-591-7098

Major funding source: Federal

Phase: Recently Completed

UPC: 110793

State ID: 0019-140-067,C501, P101

Federal ID: NHPP-5102(182)

Lat/Long: 36.706667, -81.995833

Locality: Washington