Coming Soon: Boundary Channel Drive at I-395 Interchange Improvements in Arlington County

Cost and schedule ►

Public outreach ►

This project will upgrade the Boundary Channel Drive at I-395 interchange. Improvements include:

  • Reducing Boundary Channel Drive from four lanes to two in order to construct a eight-foot-wide eastbound sidewalk and a twelve-foot-wide westbound shared-use path 
  • Installing roundabouts on Boundary Channel Drive just west and east of I-395
  • Reconfiguring the ramps between I-395 and Boundary Channel Drive
  • Adding crosswalks along Boundary Channel Drive

The project also features a new shared-use path linking the Mount Vernon Trail to Long Bridge Park.

Estimated Costs
Preliminary Engineering - $509,000
Right of Way Acquisition and Utility Relocation - $550,000
Construction - $18.6 million
Total - $19.6 million

This project is financed with state (including Revenue Sharing), Arlington County and Northern Virginia Transportation Authority funding.

Benefits 

This project aims to improve safety and traffic flow, and enhance accessibility and connectivity for bicyclists and pedestrians.

Major Milestones 

Virtual Design Public Hearing - November 2020
Begin Design-Build Procurement - February 2021
Award Design-Build Contract - June 2021
Begin Construction - Summer 2022
Final Completion - Fall 2023

Resources

Contact Info:

Mark Gibney, P.E., PMP, DBIA
Construction
703-259-2734

Scott Burdick
Construction
703-259-3371

Other relevant links:

Categorical Exclusion - January 2018

Previous Meetings >>

Phase: Coming Soon

UPC: 116394

State ID: 6587-000-R89, P101, R201, C501

Federal ID: NHPP-5B01 (120)

Lat/Long: 38.870075, -77.046587

Locality: Arlington

Page last modified: Oct. 21, 2021