In Design: Compton Road Shared-Use Path in Fairfax County

Cost and schedule ►

Public outreach ►

Please note: A virtual design public hearing will be held Monday, June 27 (in case an alternate date is needed, the meeting will be held Thursday, July 14) at 7 p.m., read more in the ad.

This project will construct a ten-foot-wide shared-use path along northbound Compton Road (Route 658) from the Bull Run Special Events Center Access Road to just south of the I-66 bridge, and from just north of the I-66 bridge to a connection with the existing Cub Run Trail. The project also includes widening the Compton Road bridge over Cub Run to accommodate the new shared-use path. The portion of the shared-use path under the I-66 bridge is being constructed separately as part of the Transform 66 Outside the Beltway Project.

Estimated Costs
Preliminary Engineering - $1.5 million
Right of Way Acquisition and Utility Relocation - $1.1 million
Construction - $5.3 million
Total - $7.9 million

This project is financed with federal, state and local funds.

Benefits 

This project aims to improve bicyclist and pedestrian safety, accessibility and connectivity to the Cub Run Trail system.

Major Milestones 

Virtual Public Information Meeting - December 2021
Virtual Design Public Hearing - June 27, 2022
Begin Right of Way Acquisition - Spring 2023
Begin Construction - Summer 2024

Resources

Contact Info:

Hong "Jenny" Ha, P.E.
Location & Design
703-259-2907

Andrew Beacher, P.E.
Preliminary Engineering
703-259-2239

Other relevant links:

Virtual Design Public Hearing Ad - June 27, 2022

Virtual Public Information Meeting VideoPresentationComment SheetNews ReleaseAd and Meeting Details - December 2021

Right of Way and Utilities Webpage

Phase: In Design

UPC: 115604

State ID: 0658-029-461, B652, C501, P101, R201

Federal ID: CMAQ-5B01 (106)

Lat/Long: 38.821031, -77.465777

Locality: Fairfax

Page last modified: May 20, 2022